Glenelg to Adelaide Pipeline
Friday, March 07, 2008This project is the first full alliance project undertaken in South Australia. The pipeline route traverses a mixture of terrain, and private and public corridors. A preliminary design was developed allowing a cost estimate to be prepared in preparation for submitting a TOC to SA Water.
The project particulars are as follows;
-
35ML/day Treatment Plant capable of 6.5 log removal;
-
3 pump stations;
-
10km of 750mm pipeline from the Glenelg Waste Water Treatment Plant to Adelaide Parklands; and
-
40km of ring main in the Adelaide Park Lands – in sizes ranging from 550mm to 150mm